Are you guys looking for Civil Engineering MCQ Questions with Answers PDF Free Download as per Civil Engineering new exam pattern? You came to the right page. This may assist you to understand and check your knowledge about the Subjects. Students also can take a free test of the Multiple Choice Questions of Civil Engineering. Each question has four options followed by the right answer. These Civil Engineering MCQ Questions are selected supported by the newest exam pattern.
Q1. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
(A) Concrete
(B) Loose sand
(C) Asphalt
(D) Firm earth
Answer: (B) Loose sand
Q2. Interfering float is the difference between
(A) Total float and free float
(B) Total float and independent float
(C) Free float and independent float
(D) None of the above
Answer: (A) Total float and free float
Q3. The independent float affects only
(A) Preceding activities
(B) Succeeding activities
(C) The particular activity involved
(D) None of the above
Answer: (C) The particular activity involved
Q4. Which of the following earth moving machines has the shortest cycle time?
(A) Drag line
(B) Hoe
(C) Clam shell
(D) Dipper shovel
Answer:(D) Dipper shovel
Q5. While filling the tender for any work, the contractor considers
(A) Site survey
(B) Availability of construction materials
(C) Availability of labour
(D) All the above
Answer: (D) All the above
Q6. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
(A) Duration
(B) Total float
(C) Free float
(D) Interfering float
Answer: (C) Free float
Q7. Updating may result in
(A) Change of critical path
(B) Decrease of project completion time
(C) Increase of project completion time
(D) All of the above
Answer:(D) All of the above
Q8. An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
(A) Rs. 8,43,750
(B) Rs. 8,75,000
(C) Rs. 10,50,000
(D) Rs. 11,56,250
Answer: (A) Rs. 8,43,750
Q9. The part of a derrick crane include
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
Of these statements
(A) (i), (ii) and (iv) are correct
(B) (ii), (iii) and (iv) are correct
(C) (i), (iii) and (iv) are correct
(D) (i), (ii) and (iii) are correct
Answer: (D) (i), (ii) and (iii) are correct
Q10. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
(A) Total float
(B) Free float
(C) Interfering float
(D) Independent float
Answer: (D) Independent float
Q11. Pick up the incorrect statement from the following:
(A) The various functions under each activity, are shown by one bar on Bar Charts
(B) Bar chart establishes the interdependency of one event on another
(C) Only approximate percentage of the completed work is reported
(D) None of these
Answer: (B) Bar chart establishes the interdependency of one event on another
Q12. Site order book is used for recording
(A) Instructions by the executive engineers
(B) Construction measurements
(C) Issue of store equipments
(D) Names of the casual labour
Answer: (A) Instructions by the executive engineers
Q13. During the construction period, price variation clause in contracts caters to
(A) Increase in rates of only important materials
(B) Variation in cost in materials element, labour element and petrol-oil-lubricant element
(C) Variation in total cost of the project on an ad hoc basis
(D) Rate of inflation
Answer: (B) Variation in cost in materials element, labour element and petrol-oil-lubricant element
Q14. A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:
Drive wheels: 25000 kg
Scraper wheels: 10000 kg
If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
(A) 10000 kg
(B) 12500 kg
(C) 22500 kg
(D) 5000 kg
Answer: (B) 12500 kg
Q15. If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
(A) 30 kg
(B) 300 kg
(C) 900 kg
(D) 1000 kg
Answer: (C) 900 kg
Construction Planning and Management MCQ
- Construction Planning and Management Objective Questions and Answers – Set 01
- Civil Construction Multiple Choice Questions – Set 02
- Construction Planning MCQ Practice Test – Set 03
- Construction Planning and Management MCQ Quiz – Set 04
- Civil Engineering Construction Management Questions – Set 05
- Study Materials Construction Planning and Management – Set 06
- Construction Planning and Management MCQ – Set 07
- Construction Planning Objective Questions and Answers – Set 08
- Construction Management Objective Questions and Answers – Set 09
- Civil Construction Planning Objective Questions – Set 10
- Construction Planning and Management Practice Test Set – 11
We hope the given Construction Planning and Management on Civil Engineering MCQ Questions with Answers will definitely yield fruitful results. Hope you got enough ideas on the Construction Planning and Management MCQs on Civil Engineering. If you have any queries related to Civil Engineering MCQs Multiple Choice Questions with Answers, drop your questions below and will get back to you in no time.