Are you guys looking for Civil Engineering MCQ Questions with Answers PDF Free Download as per Civil Engineering new exam pattern? You came to the right page. This may assist you to understand and check your knowledge about the Subjects. Students also can take a free test of the Multiple Choice Questions of Civil Engineering. Each question has four options followed by the right answer. These Civil Engineering MCQ Questions are selected supported by the newest exam pattern.
Q1. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
(A) Ice
(B) Concrete
(C) Loose sand
(D) Earth
Answer: (D) Earth
Q2. The first method invented for planning projects, was
(A) Bar chart method
(B) Milestone chart
(C) Critical path method (CPM)
(D) Programme Evaluation and Review Technique (PERT)
Answer: (A) Bar chart method
Q3. Consider the following statements:
Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control.
Of these statements
(A) 1, 3 and 4 are correct
(B) 2, 3 and 4 are correct
(C) 1, 2 and 3 are correct
(D) 1, 2 and 4 are correct
Answer:(C) 1, 2 and 3 are correct
Q4. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
(A) (a + m + b)/6
(B) (a + 2m + b)/6
(C) (a + 4m + b)/6
(D) (a + 5m + b)/6
Answer: (C) (a + 4m + b)/6
Q5. The performance of a specific task in CPM, is known
(A) Dummy
(B) Event
(C) Activity
(D) Contract
Answer: (C) Activity
Q6. Residential buildings are treated as
(A) Light construction
(B) Heavy construction
(C) Industrial construction
(D) Private construction
Answer: (A) Light construction
Q7. Which one of the following is not an excavating and moving type of equipment?
(A) Bulldozer
(B) Clam shell
(C) Scraper
(D) Dump truck
Answer: (D) Dump truck
Q8. The difference between the time avail-to do a job and the time required to do the job, is known as
(A) Event
(B) Float
(C) Duration
(D) Constraint
Answer:(B) Float
Q9. Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth.
(iv) Output can be increased by increasing the size of shovel.
Of these statements
(A) (ii), (iii) and (iv) are correct
(B) (i), (ii) and (iv) are correct
(C) (i), (iii) and (iv) are correct
(D) (i) and (iv) are correct
Answer: (B) (i), (ii) and (iv) are correct
Q10. Pre-tender stage requires
(A) Acquisition of land
(B) Selection of site
(C) Fmalisation of alignment of work
(D) All the above
Answer: (D) All the above
Q11. Consider the following statements:
In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.
Of these statements
(A) 1, 2 and 3 are correct
(B) 1 and 4 are correct
(C) 2, 3 and 4 are correct
(D) 1, 2 and 4 are correct
Answer:(B) 1 and 4 are correct
Q12. The main disadvantage of line organization, is
(A) Rigid structure
(B) Extraordinary delay in communications
(C) Top level executions over work
(D) All the above
Answer: (D) All the above
Q13. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
(A) 2 kg/tonne
(B) 6 kg/tonne
(C) 9 kg/tonne
(D) 20 kg/tonne
Answer:(C) 9 kg/tonne
Q14. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
(A) to + 3tm+ tp/3
(B) to + 4tm+ tp/4
(C) to + 4tm+ tp/5
(D) to + 4tm+ tp/6
Answer: (D) to + 4tm+ tp/6
Q15. An event is indicated on the network by a number enclosed in
(A) A circle
(B) A square
(C) A triangle
(D) All the above
Answer: (D) All the above
Construction Planning and Management MCQ
- Construction Planning and Management Objective Questions and Answers – Set 01
- Civil Construction Multiple Choice Questions – Set 02
- Construction Planning MCQ Practice Test – Set 03
- Construction Planning and Management MCQ Quiz – Set 04
- Civil Engineering Construction Management Questions – Set 05
- Study Materials Construction Planning and Management – Set 06
- Construction Planning and Management MCQ – Set 07
- Construction Planning Objective Questions and Answers – Set 08
- Construction Management Objective Questions and Answers – Set 09
- Civil Construction Planning Objective Questions – Set 10
- Construction Planning and Management Practice Test Set – 11
We hope the given Construction Planning and Management on Civil Engineering MCQ Questions with Answers will definitely yield fruitful results. Hope you got enough ideas on the Construction Planning and Management MCQs on Civil Engineering. If you have any queries related to Civil Engineering MCQs Multiple Choice Questions with Answers, drop your questions below and will get back to you in no time.